Power Mech Order Book Hit: ₹1,563 Cr BESS Contract Cancelled by WBSEDCL

NSE

POWERMECH

BSE

539302

Power Mech faces order book reduction after cancellation of a ₹1,563 crore battery energy storage project in West Bengal.

Project Type:

Battery Energy Storage System (BESS)

Client:

WBSEDCL (West Bengal State Electricity Distribution Company)

Order Impact:

₹1,563 Crores (Reduction)

What Happened

Power Mech Projects Limited has announced that WBSEDCL has annulled the tender process for a 250 MW / 1000 MWh Battery Energy Storage System (BESS) project at Goolberia, West Bengal.

As a result, the previously awarded Letter of Award (LoA) to its subsidiary PM Green Private Limited has been cancelled.

Reason for cancellation
  • Cancellation due to administrative and procedural exigencies
  • Explicit clarification:
    • No fault or non-compliance on Power Mech’s part

This is important — removes concerns about execution credibility

Financial Impact
  • Order book reduction: ₹1,563 crores
  • Bid Security & Performance Bank Guarantee:
    • Fully released
    • No financial penalties

Financial downside limited to lost opportunity, not cash loss

Strategic context
  • Project was part of grid-scale energy storage infrastructure
  • BESS is a key enabler of renewable energy integration

Cancellation reflects:

  • Policy / administrative uncertainties
  • Early-stage nature of large-scale BESS adoption in India

Source Document: Click Me