Renewable Energy Capacity Addition
Adani Green Energy Operationalizes 150 MW Solar Power Project at Khavda, Gujarat
NSE
adanigreen
BSE
541450
Adani Green Energy Limited (AGEL), through its wholly-owned stepdown subsidiary, has operationalized a 150 MW solar power project at Khavda, Gujarat, taking its total operational renewable generation capacity to 19,735.8 MW.
PRICE-SENSITIVE TRIGGER
Event: Commissioning operationalization of solar power project
Type: Renewable Energy Capacity Addition
Impact: Positive
Immediate Effect: The commissioning increases AGEL’s operational renewable energy capacity and strengthens its renewable energy portfolio at the Khavda renewable energy park.

Key Metrics:
- Newly operationalized solar power capacity: 150 MW
- Total operational renewable generation capacity after commissioning: 19,735.8 MW
- Total operational BESS capacity: 1,376 MWh
- Operationalization date: May 10, 2026
Highlight:
- AGEL crossed 19.7 GW operational renewable generation capacity after commissioning the new 150 MW project.
What Happened ?
Adani Green Energy Twenty Five C Limited (AGE25CL), a wholly-owned stepdown subsidiary of Adani Green Energy Limited (AGEL), operationalized a 150 MW solar power project at Khavda, Gujarat.
The company stated that after obtaining relevant clearances, it commenced power generation from the plant effective May 10, 2026.
With this addition, AGEL’s total operational renewable generation capacity has increased to 19,735.8 MW, while operational Battery Energy Storage System (BESS) capacity stands at 1,376 MWh.
key highlights
Project Operationalization Details:
- The project is located at Khavda, Gujarat.
- The operationalized project capacity is 150 MW.
- The project has been commissioned through AGEL’s wholly-owned stepdown subsidiary AGE25CL.
- Power generation commenced from May 10, 2026.
- The operationalization decision was taken at 7:40 PM on May 10, 2026 after receiving relevant approvals and clearances.
- AGEL’s operational renewable generation portfolio now stands at 19,735.8 MW.
- Operational BESS capacity stands at 1,376 MWh.
Note:
- Khavda is one of India’s largest renewable energy development zones and remains strategically important for AGEL’s long-term renewable expansion plans.
Risk Analysis
Key Risks
- Renewable energy generation depends on solar irradiation conditions.
- Grid evacuation and transmission infrastructure availability remain critical.
- Regulatory approvals and policy changes could impact future expansion plans.
- Large-scale renewable projects involve high capital intensity and execution complexity.
- BESS integration and operational efficiency remain important for stable energy delivery.
Worst Case Scenario
- Any delays in transmission connectivity, operational inefficiencies, or renewable generation underperformance could reduce expected returns from the project.
Risk Level: Medium
Company Commentary
- AGEL confirmed operationalization of the 150 MW solar power project at Khavda.
- The company highlighted that total operational renewable generation capacity has reached 19,735.8 MW.
- AGEL also emphasized its operational BESS capacity of 1,376 MWh.
- Power generation from the plant commenced effective May 10, 2026.
Official Exchange Filing: Adani Green Energy Limited