Capacity Expansion / Joint Venture Agreement
NTPC and UPRVUNL Sign Supplementary JV Agreement to Expand Meja Stage-II Capacity to 2,400 MW
NSE
NTPC
BSE
532555
NTPC Limited and Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL) have signed Supplementary Joint Venture Agreement (SJVA-III) for Meja Urja Nigam Private Limited (MUNPL), incorporating provisions for capacity enhancement of the Meja Stage-II thermal power project from 2×660 MW to 3×800 MW.
PRICE-SENSITIVE TRIGGER
Event: Signing of Supplementary Joint Venture Agreement (SJVA-III)
Type: Capacity Expansion / Joint Venture Agreement
Impact: Positive
Immediate Effect: The agreement formally incorporates the expansion of Meja Stage-II capacity within the JV framework, strengthening NTPC’s long-term power generation portfolio and supporting future capacity growth.

Key Metrics:
- Existing Meja Stage-II Capacity: 2 × 660 MW (1,320 MW)
- Revised Meja Stage-II Capacity: 3 × 800 MW (2,400 MW)
- Incremental Capacity Addition: 1,080 MW
- JV Structure: 50:50 Joint Venture between NTPC and UPRVUNL
Highlight:
- Capacity Expansion: Meja Stage-II capacity proposed to increase from 1,320 MW to 2,400 MW, representing an additional 1,080 MW generation capacity.
What Happened ?
NTPC Limited and Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL) executed Supplementary Joint Venture Agreement-III (SJVA-III) on June 4, 2026, in Lucknow for their joint venture company, Meja Urja Nigam Private Limited (MUNPL).
The supplementary agreement incorporates provisions relating to the expansion of the Meja Stage-II thermal power project. Under the revised framework, the project capacity is proposed to increase from the existing configuration of 2×660 MW to 3×800 MW.
MUNPL operates as a 50:50 joint venture between NTPC and UPRVUNL, and the revised agreement updates the existing JV arrangement to accommodate the larger generation project.
Key Details
Meja Stage-II Expansion Framework:
- NTPC and UPRVUNL signed SJVA-III on June 4, 2026.
- The agreement pertains to Meja Urja Nigam Private Limited (MUNPL).
- MUNPL is a 50:50 joint venture between NTPC and UPRVUNL.
- The supplementary agreement incorporates provisions related to capacity enhancement.
- Meja Stage-II capacity will be revised from 2 units of 660 MW each to 3 units of 800 MW each.
- Total project capacity will increase from 1,320 MW to 2,400 MW.
- The agreement was executed in Lucknow.
- Senior officials from NTPC, UPRVUNL and MUNPL participated in the signing ceremony.
Note:
- The signing of SJVA-III is a structural project milestone that enables the revised capacity framework to be incorporated into the joint venture agreement governing MUNPL.
Risk Analysis
Summary:
- While the agreement supports future growth, the project remains subject to execution, regulatory approvals, capital expenditure requirements, and construction timelines associated with large-scale thermal power expansion projects.
Key Risks:
- Project execution risks associated with large power generation assets.
- Potential delays in approvals, procurement, or construction schedules.
- Cost escalation risks during project implementation.
- Environmental and regulatory compliance requirements.
- Long gestation period before commercial benefits are realized.
Worst Case Scenario:
- Project delays, cost overruns, or approval-related challenges could postpone capacity addition and impact expected returns from the expansion.
Risk Level: Medium
Company Commentary
- NTPC and UPRVUNL have signed SJVA-III for MUNPL.
- The agreement incorporates provisions for enhancement of Meja Stage-II capacity.
- MUNPL continues to operate as a 50:50 joint venture between NTPC and UPRVUNL.
- The revised project configuration increases capacity from 2×660 MW to 3×800 MW.
- Senior officials from NTPC, UPRVUNL and MUNPL were present during the signing ceremony.