Capacity Expansion / Operations
Waaree Energies Commissions 3 GW Solar Module Manufacturing Capacity in Gujarat
NSE
waareeener
BSE
544277
Waaree Energies Limited has commenced operations of a new solar module manufacturing facility with a total annual capacity of 3,000 MW (3 GW) at Samakhiali, Kutch, Gujarat.
PRICE-SENSITIVE TRIGGER
Event: Commissioning of manufacturing facility
Type: Capacity Expansion / Operations
Impact: Positive
Immediate Effect: Enhances production capacity and strengthens renewable energy positioning

Key Metrics
- Total Capacity Added: 3,000 MW (3 GW)
- Units Installed: 4 lines × 750 MW each
Highlights
Capacity Expansion: 3 GW solar module manufacturing capacity operational
What Happened ?
Waaree Energies’ wholly owned subsidiary Sangam Solar One Private Limited has:
- Set up 4 solar module manufacturing lines
- Each with 750 MW annual capacity
- Totaling 3,000 MW per annum
- Location: Samakhiali, Kutch (Gujarat)
- Operations Start: April 6, 2026
Key highlights
Nature of Expansion
- Solar module manufacturing
- Renewable energy infrastructure
Capacity Addition
- 4 production lines
- 750 MW per line
- Total: 3 GW
Strategic Importance
- Strengthens domestic manufacturing
- Supports India’s solar capacity push
- Aligns with PLI & energy transition themes
Risk Analysis
Key Risks
- Demand-supply mismatch in solar modules
- Pricing pressure (global competition)
- Raw material dependency (cells/imports)
- Utilization risk
Worst Case Scenario
Low utilization → margin pressure
Risk Level: Medium
Company Commentary
- Facility successfully commissioned
- Operations commenced from April 6, 2026
Official Exchange Filing: Waaree Energies Limited