Project Commissioning
IMFA Receives Consent to Operate for Kalinganagar Greenfield Ferro Chrome Expansion; Furnace Commissioning to Begin Next Week
NSE
imfa
BSE
533047
- Indian Metals & Ferro Alloys Limited (IMFA) has announced that it has received the Consent to Operate (CTO) and Factory License for its greenfield ferro chrome expansion project at Kalinganagar (KNR-1). The approvals enable the company to commence commissioning activities for the project.
- Following the regulatory approvals, IMFA plans to initiate the switching-on process for the first furnace during the coming week. The company expects the first tapping of hot metal to take place between 15 and 20 August 2026, marking an important operational milestone for the expansion project.
PRICE-SENSITIVE TRIGGER
Event: IMFA received the Consent to Operate and Factory License for its Kalinganagar greenfield ferro chrome expansion project.
Type: Project Commissioning
Impact: Positive
Immediate Effect: The approvals allow IMFA to begin commissioning the first furnace, advancing the project from the construction phase toward commercial operations.

What Happened ?
IMFA informed the stock exchanges that it has secured the necessary regulatory approvals, including the Consent to Operate (CTO) and Factory License, for its greenfield ferro chrome expansion project at Kalinganagar (KNR-1). These approvals clear the way for commissioning activities at the facility.Â
The company stated that it will begin the process of switching on the first furnace next week and expects the first tapping of hot metal around 15–20 August 2026. A further operational update will be provided once this milestone is achieved.Â
key details
Kalinganagar Expansion Project Progress:
- IMFA has obtained the Consent to Operate (CTO) for the Kalinganagar greenfield ferro chrome expansion project.
- The company has also received the required Factory License.
- Commissioning activities will begin with the switching on of the first furnace next week.
- First tapping of hot metal is expected between 15 August and 20 August 2026.
- The company intends to issue a further update after the first successful hot metal tapping.Â
Note:
- Receiving the operational approvals marks the transition of the Kalinganagar project from the regulatory and construction stage to the commissioning phase. The commencement of furnace operations will be a key indicator of project execution and progress toward commercial production.
Risk Analysis
Summary:
- Although the project has received the required operational approvals, commissioning and furnace start-up remain subject to successful execution of the remaining commissioning activities.
Key Risks:
- Commissioning schedules may vary depending on operational readiness.
- Successful furnace start-up is required before commercial production can commence.
- The company has yet to announce the completion of the first hot metal tapping.
Worst Case:
- Any delay in commissioning or technical issues during furnace start-up could postpone the expected production timeline beyond the indicated August 15–20 window.
Risk Level: Low
Company Commentary
- The company has obtained the Consent to Operate (CTO) and Factory License for the Kalinganagar (KNR-1) expansion project.
- Switching on of the first furnace will begin next week.
- The first tapping of hot metal is expected around 15–20 August 2026.
- A further operational update will be provided in due course.
Official Exchange Filing: Indian Metals & Ferro Alloys Limited