ACME Solar Commissions Additional 33.333 MW / 160.484 MWh BESS Capacity in Rajasthan

NSE

acmesolar

BSE

544283

ACME Solar Holdings Limited announced the commissioning of an additional 33.333 MW / 160.484 MWh Battery Energy Storage System (BESS) project in Rajasthan, increasing the company’s total commissioned BESS capacity to 233.336 MW / 1123.424 MWh.

PRICE-SENSITIVE TRIGGER

Event: Commissioning of additional Battery Energy Storage System (BESS) capacity

Type: Renewable Energy Capacity Expansion

Impact: Positive

Immediate Effect: The commissioning strengthens ACME Solar’s energy storage portfolio and increases its operational renewable infrastructure capacity.

Key Metrics:

  • New BESS Capacity Commissioned: 33.333 MW
  • New Energy Storage Capacity: 160.484 MWh
  • Total Commissioned BESS Capacity: 233.336 MW
  • Total Storage Capacity: 1123.424 MWh
  • Project Location: Phalodi and Jodhpur districts, Rajasthan
  • Commercial Operation Date (COD): May 13, 2026

Highlight:

  • Label: Total Commissioned BESS Capacity
  • Value: 233.336 MW / 1123.424 MWh
What Happened ?

ACME Solar Holdings Limited informed stock exchanges that its wholly owned subsidiary, ACME Sun Power Private Limited, has commissioned an additional Battery Energy Storage System (BESS) capacity in Rajasthan.

The newly commissioned project adds 33.333 MW / 160.484 MWh capacity and is located at Village Badi Sid in Rajasthan’s Phalodi and Jodhpur districts.

Following this commissioning, ACME Sun Power’s total commissioned BESS capacity has increased to 233.336 MW / 1123.424 MWh.

key highlights

BESS Project Commissioning Details:

  • ACME Solar commissioned an additional 33.333 MW / 160.484 MWh BESS capacity.
  • The project has been commissioned through wholly owned subsidiary ACME Sun Power Private Limited.
  • The project is located at Village Badi Sid, Tehsil Bap, in Rajasthan.
  • The project spans the districts of Phalodi and Jodhpur.
  • The commissioning date was May 11, 2026.
  • Commercial Operation Date (COD) has been scheduled for May 13, 2026.
  • Total commissioned BESS capacity after this addition has reached 233.336 MW.
  • Total operational storage capacity has increased to 1123.424 MWh.
  • The announcement follows the company’s earlier disclosure dated May 4, 2026 regarding the project.

Note:

  • The commissioning further strengthens ACME Solar’s position in the growing battery energy storage and renewable infrastructure segment.
Risk Analysis

Key Risks

  • Delays in grid synchronization or regulatory approvals may impact operational ramp-up.
  • Energy storage projects require high capital expenditure and technology integration.
  • Revenue visibility may depend on long-term energy storage demand and tariff structures.
  • Battery degradation and maintenance costs may affect long-term profitability.
  • Policy changes in renewable energy and storage markets may impact returns.

Worst Case Scenario

  • Operational inefficiencies, lower storage utilization, or adverse regulatory changes could reduce expected returns from the BESS portfolio.

Risk Level: Medium

Company Commentary
  • ACME Solar confirmed the commissioning of the additional BESS capacity on May 11, 2026.
  • The company stated that the Commercial Operation Date (COD) is scheduled for May 13, 2026.
  • Management highlighted that the total commissioned BESS portfolio has now reached 233.336 MW / 1123.424 MWh.
  • The company reiterated the update under Regulation 30 of SEBI LODR Regulations.

Official Exchange Filing: ACME Solar Holdings Limited