Contract Cancellation / Project Withdrawal
BHEL Withdraws Acceptance of LOI for 800 MW Thermal Power Project
NSE
bhel
BSE
500103
Bharat Heavy Electricals Limited (BHEL) has withdrawn its acceptance of a Letter of Intent (LOI) from MB Power for the 1×800 MW Anuppur Thermal Power Project after failure to execute a formal contract within the agreed timeline
PRICE-SENSITIVE TRIGGER
Event: Withdrawal of LOI Acceptance
Type: Contract Cancellation / Project Withdrawal
Impact: Negative
Immediate Effect: Loss of potential order inflow and future revenue visibility from the project

Financial Snapshot
- Project: 1×800 MW Anuppur Thermal Power Project
- Scope: Boiler, Turbine, Generator (BTG) supply
- Counterparty: MB Power (Madhya Pradesh) Limited
Highlight:
LOI withdrawn due to failure in contract execution, impacting order pipeline
What Happened ?
BHEL announced that it has withdrawn its earlier acceptance of a Letter of Intent (LOI) received from MB Power (Madhya Pradesh) Limited.
The LOI was related to the supply of key equipment (Boiler, Turbine, Generator) for a 1×800 MW thermal power project in Anuppur
Despite multiple discussions and extensions, the formal contract could not be executed within the agreed timeline, leading to the withdrawal
key highlights
LOI Background:
- LOI initially accepted on September 3, 2025
- Related to BTG package supply
- Large-scale thermal power project
Reason for Withdrawal:
- Failure to execute formal contract within timeline
- Multiple extensions and discussions did not materialize
Disclosure Update:
- Withdrawal communicated to customer on April 17, 2026
- Official disclosure made under Regulation 30
Business Impact:
- Loss of potential large EPC/order inflow
- May affect order book visibility
Note: LOI does not guarantee revenue unless converted into a firm contract
Risk Analysis
Key Risks
- Weak conversion of LOIs into firm orders
- Impact on order book growth
- Execution uncertainty in future large projects
- Sectoral slowdown in thermal projects
Worst Case Scenario
Repeated failure in converting LOIs → declining order pipeline and revenue visibility
Risk Level: Medium
Company Commentary
- Contract could not be executed within agreed timeline
- Multiple discussions and extensions were undertaken
- Decision taken to withdraw acceptance formally
Official Exchange Filing: Bharat Heavy Electricals Limited