Order Win / EPC Contract
Bondada Engineering Secures NTPC Renewable Energy EPC Order for India’s Largest 100 MWh Vanadium Flow Battery Project
NSE
bondada
BSE
543971
- Bondada Engineering Limited has received a Notification of Award (NOA) from NTPC Renewable Energy Limited (NTPC REL) for the Engineering, Procurement and Construction (EPC) package of a 100 MWh Vanadium Redox Flow Battery Energy Storage System (VRFB BESS) at Khavda Solar Park, Gujarat.
- The project, to be executed with Delectrik Systems Pvt. Ltd. as the technology partner, includes 10 years of Operations & Maintenance (O&M) and represents India’s first and largest grid-scale VRFB energy storage project.
PRICE-SENSITIVE TRIGGER
Event: Bondada Engineering receives a Notification of Award from NTPC Renewable Energy Limited for a 100 MWh Vanadium Redox Flow Battery Energy Storage System project.
Type: Order Win / EPC Contract
Impact: Positive
Immediate Effect: The order marks Bondada Engineering’s entry into large-scale long-duration energy storage (LDES) projects, expands its renewable EPC portfolio, and strengthens its position in India’s rapidly growing Battery Energy Storage System (BESS) sector.

highlight:
- Project Scope: EPC package for a 100 MWh Vanadium Redox Flow Battery Energy Storage System (VRFB BESS) including 10 years of Operations & Maintenance.
What Happened ?
Bondada Engineering Limited announced that it has secured a Notification of Award (NOA) from NTPC Renewable Energy Limited for developing a 100 MWh Vanadium Redox Flow Battery Energy Storage System (VRFB BESS)at Khavda Solar Park, Gujarat.
The project will be executed with Delectrik Systems Pvt. Ltd. serving as the technology partner. Besides engineering, procurement, and construction, the contract also includes 10 years of operations and maintenance, making it one of the company’s most significant energy storage projects to date. The company stated that this is India’s first and largest grid-scale VRFB BESS project, positioning Bondada among the early adopters of advanced long-duration energy storage technologies.
key details
Order Scope:
- Notification of Award received from NTPC Renewable Energy Limited (NTPC REL).
- EPC package for a 100 MWh Vanadium Redox Flow Battery Energy Storage System (VRFB BESS).
- Project location: Khavda Solar Park, Gujarat.
- Includes 10 years of Operations & Maintenance (O&M).
- Technology partner: Delectrik Systems Pvt. Ltd.
- Project execution period: 10 months from receipt of the NOA.
Strategic Significance:
- Represents India’s first and largest grid-scale Vanadium Redox Flow Battery (VRFB) project.
- Marks Bondada’s expansion into Long Duration Energy Storage (LDES) solutions.
- Strengthens the company’s renewable EPC and battery storage portfolio.
- Enhances execution capabilities in next-generation clean energy infrastructure.
- Supports India’s transition toward large-scale renewable energy integration.
Why VRFB Technology Matters:
According to the company, Vanadium Redox Flow Battery (VRFB) technology offers several advantages over conventional Lithium Iron Phosphate (LFP) battery systems:
- Operational life exceeding 25 years.
- High intrinsic safety.
- Stable performance under frequent charging and discharging cycles.
- Near-zero degradation over long operating periods.
- Lower long-term operating expenditure.
- Reduced dependence on imported battery cells due to India’s domestic vanadium resources.
Industry Opportunity:
- The company highlighted that India has set a target of deploying approximately 236 GWh of Battery Energy Storage Systems by 2030, compared with the current installed capacity of around 3.3 GWh.
- This indicates substantial long-term growth potential for energy storage infrastructure driven by renewable energy expansion and grid stability requirements.
Note:
- The filing does not disclose the monetary value of the contract.
- It confirms that the project is awarded by a domestic entity, is not a related-party transaction, and that the promoter group has no interest in the awarding entity.
Risk Analysis
Summary:
- The project significantly enhances Bondada Engineering’s positioning in the emerging energy storage sector. However, execution, technology adoption, and commercialization of long-duration energy storage remain key factors influencing long-term benefits.
Key Risks:
- Project execution within the stipulated 10-month timeline.
- Successful deployment of advanced VRFB technology at grid scale.
- Technology performance over long operating cycles.
- Future market adoption of long-duration energy storage solutions.
- Cost management and execution risks associated with large EPC projects.
Worst Case:
- Any delay in project execution, technology implementation challenges, or slower adoption of VRFB systems could postpone revenue recognition and affect profitability from the project.
Risk Level: Medium
Company Commentary
- NTPC Renewable Energy has awarded Bondada Engineering the EPC package for a 100 MWh VRFB BESSproject.
- The contract includes 10 years of Operations & Maintenance.
- The company believes the order demonstrates its engineering expertise and execution capability in large-scale renewable projects.
- Management views the project as a milestone in entering the long-duration energy storage market.
- Bondada reaffirmed its commitment to supporting India’s clean energy transition through innovative and technologically advanced infrastructure solutions.
Official Exchange Filing: Bondada Engineering Limited