Road Construction Contract
Ceigall India Secures Four Arunachal Pradesh Highway Orders Worth ₹2,149.62 Crore
NSE
ceigall
BSE
544223
- Ceigall India Limited, through a joint venture with Sushee Infra Mining Limited, has received four Letters of Acceptance from the Ministry of Road Transport & Highways for road construction projects on NH-913 (Frontier Highway) in Arunachal Pradesh.
- The aggregate bid cost of the four orders is ₹2,149.62 crore, with Ceigall holding a 74% stake in the joint venture.
PRICE-SENSITIVE TRIGGER
Event: Ceigall India Limited, jointly with Sushee Infra Mining Limited, has received four Letters of Acceptance (LOAs) from the Ministry of Road Transport & Highways (MoRTH) for road construction projects on NH-913, also known as the Frontier Highway, in Arunachal Pradesh.
Type: Order Win / Road Construction Contract
Impact: Positive
Immediate Effect: The four LOAs add an aggregate ₹2,149.62 crore bid-cost order book opportunity to the Ceigall-Sushee Infra Mining joint venture, with Ceigall holding a 74% share in the JV. The projects have construction periods ranging from 36 to 48 months, followed by five-year maintenance periods.

Metrics:
Key Financial Metrics:
- Aggregate Bid Cost: ₹2,149.62 crore
- Ceigall’s JV Share: 74%
- Implied Bid Cost Attributable to Ceigall’s JV Share: Approximately ₹1,590.72 crore*
- Project 1 Bid Cost: ₹521.00 crore
- Project 2 Bid Cost: ₹611.10 crore
- Project 3 Bid Cost: ₹525.00 crore
- Project 4 Bid Cost: ₹492.52 crore
*Calculated as 74% of the aggregate ₹2,149.62 crore bid cost. This is an implied JV-share value, not disclosed revenue or order-book accounting by Ceigall.
Highlight:
- Four MoRTH LOAs carry an aggregate bid cost of ₹2,149.62 crore, with Ceigall India holding a 74% stake in the joint venture.
What Happened ?
Ceigall India Limited has received four Letters of Acceptance from the Ministry of Road Transport & Highways (MoRTH) through its joint venture with Sushee Infra Mining Limited. Ceigall holds 74% of the JV, while Sushee Infra Mining holds the remaining 26%.
The four projects involve construction of different stretches of NH-913 (Frontier Highway) in Arunachal Pradesh under the Engineering, Procurement and Construction (EPC) mode. The aggregate bid cost of the projects is ₹2,149.62 crore.
The projects carry construction periods of either 36 months or 48 months, followed by a five-year maintenance period for each project.
key details
Four NH-913 Highway Projects:
- Project 1: Construction from km 0.000 to km 55.725 of the Huri-Taliha section of NH-913 (Frontier Highway)
- Bid Cost: ₹521.00 crore
- Construction Period: 36 months
- Maintenance Period: 5 years
- Tender ID: 2025_MoRTH_868241_1
- Project 2: Construction from km 0.000 to km 78.38 of the Sarli-Huri section of NH-913 (Frontier Highway)
- Bid Cost: ₹611.10 crore
- Construction Period: 36 months
- Maintenance Period: 5 years
- Tender ID: 2025_MoRTH_868225_1
- Project 3: Construction from km 55.725 to km 113.25 of the Huri-Taliha section of NH-913 (Frontier Highway)
- Bid Cost: ₹525.00 crore
- Construction Period: 48 months
- Maintenance Period: 5 years
- Tender ID: 2025_MoRTH_868246_1
- Project 4: Construction from km 160.75 to km 209.90 of the Huri-Taliha section of NH-913 (Frontier Highway)
- Bid Cost: ₹492.52 crore
- Construction Period: 36 months
- Maintenance Period: 5 years
- Tender ID: 2025_MoRTH_868268_1
Contract Structure:
- Awarding Authority: Ministry of Road Transport & Highways
- Contract Mode: Engineering, Procurement and Construction (EPC)
- Nature: Road construction
- Entity Type: Domestic
- JV: Ceigall India Limited and Sushee Infra Mining Limited
- Ceigall JV Stake: 74%
- Sushee Infra Mining Stake: 26%
- Related Party Transaction: No
- Promoter/Promoter Group Interest in Awarding Entity: No
Project Execution:
- The four contracts have construction timelines ranging from 36 to 48 months, followed by five-year maintenance obligations.
- This provides a multi-year execution pipeline for the joint venture rather than a short-duration order.
- The projects cover multiple stretches of NH-913 in Arunachal Pradesh, including the Huri-Taliha and Sarli-Huri sections, expanding the JV’s exposure to large-scale highway construction in the state.
Note:
- The ₹2,149.62 crore figure represents the aggregate bid cost disclosed by the company.
- The filing does not provide the accounting treatment, expected revenue recognition schedule, project margins or the amount that will be recognised in Ceigall India’s standalone or consolidated financial statements.
Risk Analysis
Summary:
- The four LOAs materially expand the JV’s project pipeline, but execution will span three to four years of construction followed by five-year maintenance obligations. Large EPC road projects also carry execution, cost and terrain-related risks.
Key Risks:
- Three projects have 36-month construction periods, while one project has a 48-month construction period.
- All four projects carry five-year maintenance periods after construction.
- The projects involve multiple stretches of NH-913 in Arunachal Pradesh, requiring execution across a geographically challenging region.
- The filing does not disclose project margins or expected profitability.
- The disclosed ₹2,149.62 crore represents bid cost and should not automatically be treated as equivalent to recognised revenue.
- Execution across several projects simultaneously could increase working-capital and project-management requirements.
Worst Case:
- Construction delays, cost escalation or operational difficulties during execution could reduce project profitability or delay revenue recognition and cash flows from the awarded projects.
Risk Level: Medium
Company Commentary
- Ceigall India stated that it has jointly received four Letters of Acceptance from MoRTH through its JV with Sushee Infra Mining Limited.
- The company disclosed that Ceigall holds 74% and Sushee Infra Mining holds 26% in the joint venture.
- The four LOAs have an aggregate bid cost of ₹2,149.62 crore.
- The projects will be executed under the Engineering, Procurement and Construction (EPC) mode.
- The company disclosed that the projects include construction and subsequent five-year maintenance obligations, with construction periods ranging from 36 to 48 months.
Official Exchange Filing: Ceigall India Limited — Intimation pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015