Capacity Expansion / Project Completion
Lloyds Metals Commissions Second 4 MTPA Pellet Plant at Konsari; Total Capacity Doubles to 8 MTPA
NSE
lloydsme
BSE
512455
Lloyds Metals & Energy Limited has successfully commissioned its second 4 MTPA pellet plant at Konsari, doubling total pellet capacity to 8 MTPA, achieved in a record 16 months timeline
PRICE-SENSITIVE TRIGGER
Event: Commissioning of Pellet Plant
Type: Capacity Expansion / Project Completion
Impact: Positive
Immediate Effect: Significant increase in production capacity and strengthening of integrated steel value chain

Key Metrics:
- New Capacity Added: 4 MTPA
- Total Pellet Capacity: 8 MTPA
- Commissioning Timeline: 16 months
Highlight:
- Rapid execution → strong operational capability signal
What Happened ?
Lloyds Metals & Energy Limited announced:
- Successful commissioning of its second pellet plant at:
- Konsari, Maharashtra
- Capacity of new plant:
- 4 million tonnes per annum (MTPA)
With this:
- Total pellet capacity at Konsari:
- Increased to 8 MTPA
key highlights
Project Highlight:
- Location: Konsari, Maharashtra
- Plant size: 4 MTPA
- Commissioned in record 16 months
- Second pellet plant at same site
Integration Advantage:
- Feedstock sourced from:
- Captive low-alumina iron ore mines (Surjagarh)
- Transport via:
- 85 km slurry pipeline
- Enables:
- Production of premium-grade pellets
Operational Impact:
- Existing 4 MTPA plant already at:
- 100% capacity utilization
- Combined capacity:
- 8 MTPA (Konsari)
- Enhances:
- Efficiency
- Cost competitiveness
- Pricing power
Strategic Importance:
- Strengthens end-to-end steel value chain integration
- Supports long-term:
- Capacity expansion strategy
- Demand capture in steel sector
- Reinforces execution capability
Note:
Excludes additional capacities under strategic investments (MRPPL, BRPL)
Risk Analysis
Key Risks
- Commodity price volatility (iron ore, steel)
- Demand cyclicality in steel sector
- Capacity utilization ramp-up risk
- Export market dependency
Worst Case Scenario
- If steel demand weakens, utilization and margins could be impacted despite higher capacity
Risk Level: Medium
Company Commentary
- Highlighted record execution timeline
- Emphasized integrated operations strength
- Reinforced commitment to:
- Responsible growth
- Operational excellence
- Positioned project as:
- Strategic milestone
Official Exchange Filing: Lloyds Metals & Energy Limited