Order Win / Contract Award
VA Tech WABAG Secures ‘Large’ BWSSB Order for Energy-Efficient Wastewater Treatment Projects
NSE
wabag
BSE
533269
- VA Tech WABAG Limited has secured a ‘Large’ domestic order from the Bangalore Water Supply and Sewerage Board (BWSSB) to design, build and operate two sewage treatment plants along with a tertiary treatment plant in Bengaluru.
- The project includes EPC execution, renewable energy integration through biogas-based captive power generation, and a seven-year operations and maintenance (O&M) contract, strengthening WABAG’s position in India’s municipal wastewater treatment sector.
PRICE-SENSITIVE TRIGGER
Event: BWSSB Awards Large Wastewater Treatment Project to WABAG
Type: Order Win / Contract Award
Impact: Positive
Immediate Effect: The order expands WABAG’s domestic project pipeline with a long-tenure municipal wastewater contract that combines EPC execution with seven years of recurring O&M revenue. It also reinforces the company’s leadership in sustainable water infrastructure and wastewater treatment solutions.

Metrics:
Key Metrics:
- Order Classification: Large
- Order Value Range: ₹250 crore to ₹600 crore
- Sewage Treatment Capacity: 100 MLD (Byramangala)
- Sewage Treatment Capacity: 60 MLD (Bellandur)
- Tertiary Treatment Plant: 25 MLD (Byramangala)
- EPC Execution Period: 36 months
- Operations & Maintenance: 7 years
Highlight:
- WABAG secured a ‘Large’ domestic wastewater infrastructure order from BWSSB, combining EPC execution with a seven-year O&M contract and expanding its presence in Bengaluru’s water infrastructure sector.
What Happened ?
VA Tech WABAG Limited announced that it has received a ‘Large’ order from the Bangalore Water Supply and Sewerage Board (BWSSB) for the design, build and operation of wastewater treatment facilities in Bengaluru. The project comprises a 100 MLD Sewage Treatment Plant (STP) and a 25 MLD Tertiary Treatment Plant (TTP) at Byramangala, along with a 60 MLD Sewage Treatment Plant at Bellandur.
The contract covers engineering, procurement, construction and commissioning of the facilities together with biogas-based captive power generation. Following completion of the EPC phase within 36 months, WABAG will undertake operations and maintenance for seven years, providing long-term operational support. The company also noted that it had executed the first phase of the Bellandur facility previously and has now secured the second phase, further strengthening its relationship with BWSSB.
key details
Project Scope:
- WABAG has been awarded the Design, Build and Operate (DBO) contract for a 100 MLD Sewage Treatment Plant (STP) and a 25 MLD Tertiary Treatment Plant (TTP) at Byramangala, Bengaluru.
- The company has also secured the Design, Build and Operate (DBO) contract for a 60 MLD Sewage Treatment Plant (STP) at Bellandur, Bengaluru.
- The order covers the complete project lifecycle, including engineering, procurement, construction, commissioning and long-term operations.
Technology & Engineering:
- The wastewater treatment plants will be developed using the Activated Sludge Process (ASP) integrated with a Biological Nutrient Removal (BNR) system.
- The 25 MLD Tertiary Treatment Plant at Byramangala will incorporate Ultrafiltration (UF) technology to produce high-quality treated water suitable for discharge into surrounding water bodies.
- The facilities will also include biogas-based captive power generation, helping reduce greenhouse gas emissions while improving energy efficiency and operational sustainability.
Sustainability Benefits:
- The project is designed to improve Bengaluru’s wastewater treatment capacity amid increasing urbanisation.
- Renewable energy generation through biogas will lower the plants’ energy footprint and promote resource recovery.
- The facilities support circular economy principles by combining wastewater treatment with energy optimisation and water reuse.
- The project is expected to strengthen the city’s long-term water security while contributing to environmentally sustainable infrastructure development.
Long-Term Contract:
- The EPC portion of the project is scheduled for completion within 36 months.
- Following commissioning, WABAG will operate and maintain the facilities for 7 years, providing recurring service revenue and ensuring efficient plant performance over the contract period.
Strengthening Existing Relationship:
- WABAG previously executed the first phase of the Bellandur Sewage Treatment Plant.
- The award of the second phase further strengthens the company’s relationship with BWSSB and reinforces its position as a preferred partner for large municipal wastewater infrastructure projects.
Order Classification:
- The contract has been classified as a ‘Large’ domestic order under WABAG’s order categorisation framework.
- As per the company’s classification, a Large domestic order represents a project with an order inflow value ranging between ₹250 crore and ₹600 crore.
- The company also confirmed that the project is not a related-party transaction, and neither the promoter nor the promoter group has any interest in the awarding authority.
Note:
- The BWSSB order strengthens WABAG’s municipal water infrastructure portfolio by combining advanced wastewater treatment technologies with renewable energy integration and a long-term O&M commitment.
- Beyond expanding the company’s domestic order book, the project reinforces WABAG’s expertise in delivering sustainable, energy-efficient water infrastructure that supports urban water security and circular economy objectives.
Risk Analysis
Summary:
- The BWSSB order strengthens WABAG’s municipal wastewater order book and provides long-term revenue visibility through a combination of EPC execution and a seven-year O&M contract.
- However, successful project execution, timely commissioning and operational performance will be critical to realizing the full benefits of the contract.
Key Risks:
- Execution Risk: The project involves the design, engineering, procurement, construction and commissioning of multiple wastewater treatment facilities. Delays in execution could impact project timelines and cash flow realization.
- Timeline Risk: The EPC scope is scheduled to be completed within 36 months. Any delay arising from approvals, supply chain constraints or construction challenges could postpone project completion.
- Operational Performance Risk: WABAG will operate and maintain the facilities for seven years after commissioning. Maintaining treatment efficiency, plant availability and service quality throughout the contract period will be essential for successful execution.
- Technology Integration Risk: The project integrates advanced wastewater treatment technologies, including Biological Nutrient Removal (BNR), Ultrafiltration (UF) and biogas-based captive power generation. Efficient integration and commissioning of these systems will be important to achieve the intended environmental and operational outcomes.
- Public Infrastructure Dependency: As the project is awarded by a government utility, execution remains subject to coordination with public authorities and adherence to contractual milestones throughout the implementation period.
Worst Case:
- If project execution is significantly delayed or operational performance does not meet contractual requirements, commissioning timelines, revenue recognition and expected long-term operational benefits from the contract could be adversely affected.
Risk Level: Low
Company Commentary
- WABAG stated that securing the two BWSSB projects reinforces its leadership in India’s municipal wastewater treatment sector.
- The company believes the energy-efficient wastewater treatment facilities, integrated with biogas-based power generation, will serve as a scalable model for resource recovery, circularity and energy optimisation.
- Management highlighted that the projects will significantly enhance Bengaluru’s sewage treatment capacitywhile promoting environmentally responsible wastewater management and supporting Karnataka’s long-term water security objectives.
- WABAG emphasized that the facilities will strengthen the sustainability and resilience of Bengaluru’s water ecosystem by combining advanced treatment technologies with renewable energy generation.
- The company reiterated its commitment to delivering sustainable, resilient and future-ready water infrastructure through innovative technologies and efficient lifecycle project management.
Official Exchange Filing: VA Tech WABAG Limited